Preview only show first 10 pages with watermark. For full document please download

Pmr/gmr Series Installation And Operation Manual

   EMBED


Share

Transcript

FlexNet ™ PMR, GMR Series Fiber Enclosures Installation and Operation Manual PMR-S1, PMR-S2, GMR-S1, GMR-S2 FlexNet Fiber Series Enclosures Effective: March 2006 Alpha Technologies Power Alpha Technologies ® FlexNet Fiber Enclosures Installation and Operation Manual 031-239-C0-003, Rev. C Effective Date: March 2006 Copyright© 2006 Alpha Technologies, Inc. a member of the Alpha Group NOTE: Alpha denies responsibility for any damage or injury involving its enclosures, power supplies, generators, batteries or other hardware, manufactured by Alpha or members of the Alpha Group, when used for an unintended purpose, installed or operated in an unapproved manner, or improperly maintained. NOTE: Photographs and drawings contained in this manual are only for illustrative purposes. These photographs and drawings my not exactly match your installation. NOTE: Review the written and illustrative information contained in this manual before proceeding. If there are questions regarding the safe installation or operation of this product, please contact Alpha Technologies or your nearest Alpha representative. Contacting Alpha Technologies: www.alpha.com or For general product information and customer service (7 AM to 5 PM, Pacific Time), call 1-800-863-3930 For complete technical support, call 1-800-863-3364 7 AM to 5 PM, Pacific Time or 24/7 emergency support Table of Contents Safety Notes .......................................................................................................................... 7 1.0 Introduction ............................................................................................................... 10 1.1 FlexNet™ Fiber Enclosures ........................................................................... 10 1.2 PMR-S1 and -S2 (Pole Mount) Enclosures ....................................................11 1.3 GMR-S1 and -S2 (Ground Mount) Enclosures .............................................. 16 2.0 Specifications............................................................................................................ 18 2.1 PMR (Pole Mount) Specifications .................................................................. 18 2.2 GMR (Ground Mount) Specifications ............................................................. 19 3.0 Installation................................................................................................................. 20 3.1 PMR (Pole Mount) Installations ..................................................................... 20 3.1.1 Wooden Pole ...................................................................................... 20 3.1.2 Enclosure on Short Pole with Battery Vault......................................... 22 3.1.3 Enclosure on Steel/Concrete Pole ...................................................... 24 3.2 GMR (Ground Mount) Installations ................................................................ 26 3.2.1 Pre-Installation .................................................................................... 26 3.3 Enclosure Grounding ..................................................................................... 28 3.4 Installing Enclosure on Pre-cast Pad ............................................................. 29 3.5 Conduit Routing Area, GMR S-1 Enclosure ................................................... 30 3.6 Conduit Routing Area, GMR S-2 Enclosure ................................................... 31 3.7 Installing on a Polymer Pedestal Support ...................................................... 32 4.0 Equipping the System ............................................................................................... 33 4.1 Service Power ................................................................................................ 33 4.2 Batteries ......................................................................................................... 34 4.2.1 PMR Batteries ..................................................................................... 35 4.2.2 GMR Batteries..................................................................................... 36 4.3 Mounting Rail Adjustment .............................................................................. 37 4.4 Power Supply Installation............................................................................... 39 4.5 GMT Fuse Module ......................................................................................... 41 4.5.1 Installation ............................................................................................. 41 4.6 Internal Connections ...................................................................................... 42 4.7 4.8 4.9 4.6.1 System Block Diagram ........................................................................ 42 4.6.2 "Hot-Swap" Procedure ........................................................................ 43 Fiber Management Panel............................................................................... 44 Optional Fan Kit Installation (for PMR and GMR Series Enclosures) ............ 45 Optional Form C Alarm Panel Installation ...................................................... 47 4.9.1 Mounting and Wiring the Alarm Panel ................................................. 48 4 031-239-C0-003 Rev C List of Figures Fig. 1-1, Exterior Views, FlexNet Enclosures ................................................................................................... 10 Fig. 1-2, Exterior Views, PMR-S1 FlexNet Enclosure .......................................................................................11 Fig. 1-3, Interior Views, PMR-S1 FlexNet Enclosure ....................................................................................... 12 Fig. 1-4, Exterior Views, PMR-S2 FlexNet Enclosure ..................................................................................... 13 Fig. 1-5, Interior Views, PMR-S2 FlexNet Enclosure (Fixed-rack) ................................................................... 14 Fig. 1-6, Interior Views, PMR-S2 FlexNet Enclosure (Swing-rack) .................................................................. 15 Fig. 1-7, GMR-S1 FlexNet Enclosure ............................................................................................................... 16 Fig. 1-8, GMR-S2 FlexNet Enclosure ............................................................................................................... 17 Fig. 3-1, Wooden Pole Installation.................................................................................................................... 21 Fig. 3-2, Short Wooden Pole Installation .......................................................................................................... 22 Fig. 3-3, Top View ............................................................................................................................................. 23 Fig 3-4, Connection Points ............................................................................................................................... 23 Fig. 3-5 Steel/Concrete Pole Installation .......................................................................................................... 25 Fig. 3-6, GMR Positioning and Safety .............................................................................................................. 27 Fig. 3-7, Suggested Grounding Method ........................................................................................................... 28 Fig. 3-8, Layout for Precast Pad, Single-wide for GMR Series Enclosures...................................................... 29 Fig. 3-9, Conduit Routing, GMR-S1 Enclosure................................................................................................. 30 Fig. 3-10, Conduit Routing, GMR-S2 Enclosure .............................................................................................. 31 Fig. 3-11, PS-6 Standard Pedestal ................................................................................................................... 32 Fig. 3-12, PS-6XL Pedestal .............................................................................................................................. 32 Fig. 3-13, Typical Pedestal Site ........................................................................................................................ 32 Fig. 4-1, Service Power .................................................................................................................................... 33 Fig. 4-2 Battery Identification Label ................................................................................................................. 34 Fig. 4-3, Battery Installation for PMR Series .................................................................................................... 35 Fig. 4-4, Battery Installation for GMR Series .................................................................................................... 36 Fig. 4-5, Mounting Rail Adjustment, PMR Left Side ......................................................................................... 37 Fig. 4-6, Mounting Rail Adjustment, PMR Right Side ....................................................................................... 37 Fig. 4-7, Mounting Rail Adjustment, GMR Right Side....................................................................................... 37 Fig. 4-8, GMR/PMR Upper Left Side Detail ...................................................................................................... 38 Fig. 4-9, PMR Upper Right Side Detail ............................................................................................................. 38 031-239-C0-003 Rev C 5 List of Figures, continued Fig. 4-10, Lower Rail Detail .............................................................................................................................. 38 Fig. 4-11, PMR/GMR-S1 Power Supply Installation ......................................................................................... 39 Fig. 4-12, PMR/GMR-S2 Power Supply Installation ......................................................................................... 40 Fig. 4-13, Placement Tinnerman Nuts .............................................................................................................. 41 Fig. 4-14, GMT Fuse Assembly Secured to Rail .............................................................................................. 41 Fig. 4-15, GMR-S2 Location ............................................................................................................................. 41 Fig. 4-16, PMR-S2 Location ............................................................................................................................. 41 Fig. 4-17, Simplified Block Diagram ................................................................................................................. 42 Fig. 4-18, Connections, "Hot-Swapping" .......................................................................................................... 43 Fig. 4-19, Fiber Management Panel ................................................................................................................. 44 Fig. 4-20, Optional Fan Kit................................................................................................................................ 45 Fig. 4-21, Placing the Fan Unit ......................................................................................................................... 46 Fig. 4-22, Extending the Side Rails .................................................................................................................. 46 Fig. 4-23, Completed Fan Installation............................................................................................................... 46 Fig. 4-24, Form C Alarm Signal Panel .............................................................................................................. 47 Fig. 4-25, Form C Alarm Signal Panel Dimensions .......................................................................................... 47 Fig. 4-26, Attach Panel to Rack ........................................................................................................................ 48 Fig. 4-27, Wiring the Alarm Panel ..................................................................................................................... 48 List of Tables Table 2-1, PMR Specifications.......................................................................................................................... 18 Table 2-2, GMR Specifications ......................................................................................................................... 19 Table 4-1, Connections for Alarm Panel ........................................................................................................... 48 6 031-239-C0-003 Rev C Safety Notes Review the drawings and illustrations contained in this manual before proceeding. If there are any questions regarding the safe installation or operation of the system, contact Alpha Technologies or the nearest Alpha representative. Save this document for future reference. To reduce the risk of injury or death, and to ensure the continued safe operation of this product, the following symbols have been placed throughout this manual. Where these symbols appear, use extra care and attention. ATTENTION The use of ATTENTION indicates specific regulatory/code requirements that may affect the placement of equipment and /or installation procedures. NOTE: A NOTE provides additional information to help complete a specific task or procedure. CAUTION! The use of CAUTION indicates safety information intended to PREVENT DAMAGE to material or equipment. WARNING! WARNING presents safety information to PREVENT INJURY OR DEATH to the technician or user. 031-239-C0-003 Rev C 7 Battery Maintenance Guidelines The battery maintenance instructions listed below are for reference only. Battery manufacturer’s instructions for transportation, installation, storage or maintenance take precedence over these instructions. • • • • • • • • To prevent damage, inspect batteries every 3 months for: Signs of battery cracking, leaking or swelling. The battery should be replaced immediately by authorized personnel using a battery of the identical type and rating. Signs of battery cable damage. Battery cable should be replaced immediately by Authorized Personnel using replacement parts specified by vendor. Loose battery connection hardware. Refer to battery manufacturer’s documentation for the correct torque and connection hardware for the application. Apply battery manufacturer’s specified antioxidant compound on all exposed connections. Verify battery terminals and/or exposed connection hardware is not within 2 inches of a conductive surface. Reposition batteries as necessary to maintain adequate clearance. Clean up any electrolyte (battery emission) in accordance with all federal, state, and local regulations or codes. Proper venting of the enclosure is recommended. Follow the Battery Manufacturer’s approved transportation and storage instructions. Always replace batteries with those of an identical type and rating. Never install old or untested batteries. Do not charge batteries in a sealed container. Each individual battery should have at least 0.5 inches of space between it and all surrounding surfaces to allow for convection cooling. All battery compartments must have adequate ventilation to prevent an accumulation of potentially dangerous gas. Recycling and Disposal Instructions Spent or damaged batteries are considered environmentally unsafe. Always recycle used batteries or dispose of the batteries in accordance with all federal, state and local regulations. Electrical Safety • • • • • • Lethal voltages are present within the power supply and electrical boxes. Never assume that an electrical connection or conductor is not energized. Check the circuit with a volt meter with respect to the grounded portion of the enclosure (both AC and DC) prior to any installation or removal procedure. Always use the buddy system when working under hazardous conditions. A licensed electrician is required to install permanently wired equipment. Input voltages can range up to 240 VAC. Ensure that utility power is disabled before beginning installation or removal. Ensure no liquids or wet clothes contact internal components. Hazardous electrically live parts inside this unit are energized from batteries even when the AC input power is disconnected. Mechanical Safety • • • 8 Keep hands and tools clear of fans. Fans are thermostatically controlled and will turn on automatically. Power supplies can reach extreme temperatures under load. Use caution around sheet metal components and sharp edges. 031-239-C0-003 Rev C Battery Safety Notes WARNING! Lead-acid batteries contain dangerous voltages, currents and corrosive material. Battery installation, maintenance, service and replacement must be performed only by authorized personnel. Chemical Hazards Any gelled or liquid emissions from a valve-regulated lead-acid (VRLA) battery contain dilute sulfuric acid, which is harmful to the skin and eyes. Emissions are electrolytic, and are electrically conductive and corrosive. To avoid injury: • Servicing and connection of batteries shall be performed by, or under the direct supervision of, personnel knowledgeable of batteries and the required safety precautions. • Always wear eye protection, rubber gloves, and a protective vest when working near batteries. Remove all metallic objects from hands and neck. • Batteries produce explosive gases. Keep all open flames and sparks away from batteries. • Use tools with insulated handles, do not rest any tools on top of batteries. • Batteries contain or emit chemicals known to the State of California to cause cancer and birth defects or other reproductive harm. Battery post terminals and related accessories contain lead and lead compounds. Wash hands after handling (California Proposition 65). • Wear protective clothing (insulated gloves, eye protection, etc.) whenever installing, maintaining, servicing, or replacing batteries. • If any battery emission contacts the skin, wash immediately and thoroughly with water. Follow your company’s approved chemical exposure procedures. • Neutralize any spilled battery emission with the special solution contained in an approved spill kit or with a solution of one pound Bicarbonate of soda to one gallon of water. Report chemical spill using your company’s spill reporting structure and seek medical attention if necessary. • All battery compartments must have adequate ventilation to prevent an accumulation of potentially dangerous gas. • Prior to handling the batteries, touch a grounded metal object to dissipate any static charge that may have developed on your body. • Never use uninsulated tools or other conductive materials when installing, maintaining, servicing or replacing batteries. • Use special caution when connecting or adjusting battery cabling. An improperly connected battery cable or an unconnected battery cable can make contact with an unintended surface that can result in arcing, fire, or possible explosion. 031-239-C0-003 Rev C 9 1.0 Introduction 1.1 FlexNet Fiber Enclosures The PMR (pole-mount) and GMR (ground-mount) 19" rack enclosures are equipped with AC service entrances, AC distribution, and are supported by a wide range of accessories, including Alpha’s FlexNet 300W power supply and AlphaCell 85GXL batteries. These features provide extended standby runtime and life. There are two versions of each type of enclosure available, differing only in their physical size. See Section 2.0 Specifications for detailed measurements. An optional fan kit is available for both PMR and GMR enclosures (see Section 4.8, Optional Fan Kit Installation), as well as an optional Form C alarm signal panel (see Section 4.9, Optional Form C Alarm Signal Panel Installation.) The FlexNet Enclosure: • Supports FTTH processors and other hardened rack-mount equipment. • Supports FlexNet 300W UPS and AlphaCell batteries for reliable extended runtime. • Supports thermostatically controlled 48VDC and 120VAC fan and heater options. • Provides adjustable 19” EIA equipment racks — offered in either fixed or "swing" versions. • Provides a swing rack option for the PMR-S2 • Provides all aluminum construction with a durable powdercoat finish • Provides a removable door and lid. GMR-S2 GMR-S1 PMR-S2 PMR-S1 Fig. 1-1, FlexNet Enclosures 10 031-239-C0-003 Rev C 1.0 Introduction, continued 1.2 PMR-S1 and S2 (Pole Mount) Enclosures 1 19.25" 29.63" 25.55" 18.10" 1 32.21" 5 6 4 3 2 Fig. 1-2, Exterior views, PMR-S1 FlexNet Enclosure 031-239-C0-003 Rev C 1 Service entrance 4 Door latch 2 Lower mounting bracket 5 Hinged removeable door 3 Access port for portable generator 6 Optional GEM security lock 11 1.0 Introduction, continued 1.2 PMR-S1 and S2 (Pole Mount) Enclosures, continued 1 3 2 5.91" 8 A 6.0" 1.0" 15 14 3 13 24.00" 12 4 11 5 6 10 9 7 18.31" Section A-A A Fig. 1-3, Interior views, PMR-S1 FlexNet Enclosure 12 11 Bus Bar, 5 Positions 1 Pole Mount Bracket 6 2 Opt. Cooling Fan 7 Opt. Battery Retaining Bar 12 Opt. Fiber Management Panel 3 Service Entrance 8 Mounting Flange, Tamper Switch 13 Convenience Outlets 4 Door Latch 9 Access Panel, Portable Generator 14 Fixed Rack Adjustments, 7 Positions 5 Opt. 19" ELPM300 UPS Mounting Brackets Opt. ELMP300 UPS 10 Opt. AlphaCell 85GXL Batteries 15 Removeable Lid 031-239-C0-003 Rev C 1.0 Introduction, continued 1.2 PMR-S1 and S2 (Pole Mount) Enclosures, continued 1 19.2" 33.58" 18.1" 6.0" 29.50" 6.0" 1.0" 2 7 36.98" 1 6 5 8 3 4 Fig. 1-4, Exterior views, PMR-S2 FlexNet Enclosure 1 Service Entrance 5 Lockable Door Latch 2 Upper Pole Mount Bracket 6 Hinged, Removable Door 3 Lower Pole Mount Bracket 7 Fixed Rack Adjustments, 7 positions, 1" centers 4 Access Panel, Portable DC Generator 8 Optional GEM Security Lock 031-239-C0-003 Rev C 13 1.0 Introduction, continued 1.2 PMR-S1 and S2 (Pole Mount) Enclosures, continued 1 Section B-B 2 3 4 A 7 14 13 B B 22.75" 25.12" 31.00" 12 11 10 9 5 8 6 A 18.31" Section A-A Fig. 1-5, Interior views, PMR-S2 FlexNet Enclosure (Fixed-rack model) 14 1 Pole Mount Bracket 6 Optional Battery Retaining Bar 11 Optional Fiber Management Panel 2 Adj. Equip. Rack, 7 position 7 Optional Fiber Tie Bracket 12 Convenience Outlets 3 1/2", 3/4" Knockouts 8 Optional AlphaCell 85GXL Batteries 13 Optional ELPM 300 UPS 4 Service Entrance 9 Chassis Ground Lug 14 Removeable Lid 5 1/2", 3/4" Knockouts 10 Bus Bar, 5 position 031-239-C0-003 Rev C 1.0 Introduction, continued 1.2 PMR-S1 and S2 (Pole Mount) Enclosures, continued 3.04" Section A-A 1 2 10.5" 3 5 4 7 6 B 9 19 8 18 24.00" 25.75" 19.88" 17 16 A A 15 10 14 13 3 11 B 12 Section B-B 18.31" Fig. 1-6, Interior Views, PMR-S2 FlexNet Enclosure (Swing-rack Model) 1 Pole Mount Brackets 7 Tamper Switch Mount 13 AlphaCell 85GXL Batteries 2 Rack Adj Holes, 7PL, 1" Ctr 8 Swing Rack Lock Screw (2) 14 Opt. Fiber Mgmt Panel 3 Opt. Battery Retaining Bar 9 Opt. Service Entrance 15 Chassis Ground Lug 4 3/4", 1/2" Knockouts 10 3/4", 1/2" Knockouts 16 Ground Block, 5 psn 5 Opt. ELPM 300 Power Supply 11 Access Panel, Prt. Generator 17 Opt. Convenience Outlets 6 Slide Lock Screw (2 Places) 12 Lower Pole Mount Brackets 18 Upper Pole Mount Bracket 19 Removeable Lid 031-239-C0-003 Rev C 15 1.0 Introduction, continued 1.3 GMR-S1 and S2 (Ground Mount) Enclosures 20" 27.5" 1 6.00" 1.00" 2 30.9" 4 3 5 31" 23.4" 4.25" 7 6 18.3" Fig. 1-7, GMR-S1 FlexNet Enclosure 1 Gemlock door locks (2PL) 5 Access Panel for Generator or Portable Generator 2 Optional Service Entrance 6 Optional Cooling Fan 3 Lift Off Door 7 Equipment Rack (Fixed) 4 Equipment Rack Adjustment (6PL, 1" CTR.) 16 031-239-C0-003 Rev C 1.0 Introduction, continued 1.3 GMR-S1 and S2 (Ground Mount) Enclosures, continued 20" 31.0" 1 6.00" 1.00" 2 38.0" 4 3 5 31.0" 30.4" 4.25" 7 6 18.3" Fig. 1-8, GMR-S2 FlexNet Enclosure 1 Gemlock door locks (2PL) 5 Access Panel for Generator or Portable Generator 2 Optional Service Entrance 6 Optional Cooling Fan 3 Lift Off Door 7 Equipment Rack (Fixed) 4 Equipment Rack Adjustment (6PL, 1" CTR.) 031-239-C0-003 Rev C 17 2.0 Specifications 2.1 PMR (Pole Mount) Specifications PMR Component Enclosures Material Vent Screen Door and Lid Seal Hardware Color: Tamper Switch Rack Grounding Safety Ground Lid Doors Enclosure Mounting Cooling Description PMR-S1: 25.5” (64.8cm)W x 32.2” (81.8cm)H x 19.25” (48.9cm)D, Weight: 50 lbs PMR-S2: 29.5” (74.9cm)W x 37.0” (94cm)H x 19.25” (48.9cm)D, Weight: 60 lbs. Powder-coated aluminum Stainless steel fabric with .008” x .008 (.2mm x .2mm) opening size to minimize snow, water and dust intrusion Neoprene gasketing Stainless steel (excluding optional GemLocks) Gray or Pine Green (Custom colors available) Optional Internal ground bar: Eight usable lugs Adjacent to AC outlets (Bronze or optional stainless steel ground stud) Removable with lanyard Hinged lift-off removable with stainless steel spring latch and door-open prop rod; Gemlock options Galvanized steel brackets for wood, and concrete pole mount and wall mount. Natural convection (120VAC and 48VDC fan options) PMR-S2 with Swing Rack requires these fan kits: 48VDC Fan option ( Alpha p/n: 745-819-20-002) 120VAC Fan option (Alpha p/n: 745-819-21-002) Rack Mounting: EIA 19” mounting rails using Tinnerman mounting clips PMR-S1: Rail height, 27.5", 14 mounting positions Internal Mounting Rails Rack Grounding Stationary Rack Adjustment Swing Rack Adjustment: Enclosure Environmental Ratings *Fiber Strain Relief Tie Bar *Fiber Management Panel (Alpha p/n: 745-672-20) **Power Supply **Batteries *Battery Cable Kit *Battery Heater **Form C Alarm Panel (Alpha p/n: 012-308-20) PMR-S2: Stationary Rack configuration (Alpha p/n 745-804-20): Rail height, 33.5", 18 mounting positions PMR-S2: Swing Rack configuration (Alpha p/n 745-797-20): Rail height, 33.5", 14 mounting positions Rails grounded to the chassis (swing rack is isolated from chassis) Provision to move rails on 1” increments over 6” when batteries are not installed. Forward rail location supports a 12” deep flush front mounted panel with a minimum of 3.5” in front of panel to support fiber optic connectors. 7 mounting holes on 1.00" centers on upper and lower rails. Equipment space is designed to IP X5 per IEC 529. The enclosure and service entrance is rated 3R 19” mounting provides ability to strain relief fiber cable plugged into the front of communications equipment. Provides fiber slack storage and secures a splice tray using a Velcro strap. Tie wrap slots on sides permit securing fiber cables to panel. Panel can be removed from enclosure. FlexNet ELPM 300 – 300W 48VDC output with 48VDC battery bus and 19-inch reversible mounting bracket option. (Other UPS systems available.) 48VDC string of 85 GXL (50Ah) positioned on ends (negative terminal side down) with battery retaining bar. (Other types of batteries available.) Optional Optional (120VAC) Optional. Provides Form C alarm signal interface. Requires the FlexNet ELPM 300-300W power supply. *AC Service External 70A rainproof SUSE rated breaker box with four (4) internal 120VAC 20A receptacles, or two (2) 120VAC 20A and two (2) 240VAC 20A receptacles Regulatory CSA C22.2 No. 107.1-01, CSA C22.2 No. 0-M91, CSA C22.2 No. 0.4-04, CSA C22.2 No. 94-M91, UL 50, UL 1778 Notes: Table 2-1, PMR (Pole Mount) Specifications 1. Additional rack space capacity if batteries are not installed. 2. Runtime of 10 hours based on 212W load and new batteries. 3. * Optionally configured items. 4. **Optional items shipped separately. 18 031-239-C0-003 Rev C 2.0 Specifications, continued 2.2 GMR (Ground Mount) Specifications GMR Components Description Enclosures GMR-S1: 27.5” (69.9cm)W x31” (78.7cm)H x 20” (50.8cm)D, Weight: 50lbs. GMR-S2: 31” (78.7cm)W x38” (96.5cm)H x 20” (50.8cm)D, Weight 60 lbs Material Powder-coated aluminum Vent Screen Stainless steel fabric with .008” x .008 (.2mm x .2mm) opening size to minimize snow, water and dust intrusion Door and Lid Seal Neoprene gasketing Hardware Stainless steel (excluding optional GemLocks) Color Gray (Custom colors available) Tamper Switch Optional Grounding Internal ground bar: Eight usable lugs Safety Ground Adjacent to AC outlets (Bronze or optional stainless steel ground stud) Lid Removable Doors Two removable doors w/Gemlocks. Starlock option Enclosure Mounting Precast polymer concrete pad or PS-6 or PS-6XL pedestal systems Cooling Natural convection (120VAC and 48VDC fan options) 48VDC Fan option (Alpha p/n: 745-820-20-002) 120VAC Fan option (Alpha p/n: 745-820-21-002) Internal Mounting Rails Rack Mounting: EIA 19” mounting rails using Tinnerman mounting clips GMR-S1: Rail height, 27.5", 14 mounting positions GMR-S2: Rail height, 33.5", 18 mounting positions Rack Grounding Rails grounded to the chassis Adjustment Provision to move rails on 1” increments over 6” when batteries are not installed. Forward rail location supports a 12” deep flush front mounted panel with a minimum of 3.5” in front of panel to support fiber optic connectors. Enclosure Environmental Ratings Equipment space is designed to IP X5 per IEC 529. The enclosure and service entrance is rated 3R *Fiber Strain Relief Tie Bar 19” mounting provides ability to strain relief fiber cable plugged into the front of communications equipment. *Fiber Management Panel: (Alpha p/n: 745-672-20) Provides fiber slack storage and secures a splice tray using a Velcro strap. Tie wrap slots on sides permit securing fiber cables to panel. Panel can be removed from enclosures. **Power Supply FlexNet ELPM 300 – 300W 48VDC output with 48VDC battery bus and 19-inch reversible mounting bracket option. **Batteries 48VDC string of 85 GXL (50Ah) positioned on ends (negative terminal side down) **Battery Cable Kit Fused *Battery Heater Optional (120VAC) **Form C Alarm Panel (Alpha p/n: 012-308-20) Optional. Provides Form C alarm signal interface. Requires the FlexNet ELPM 300-300W power supply. *AC Service External 70A rainproof SUSE rated breaker box with four (4) internal 120VAC 20A receptacles, or two (2) 120VAC 20A and two (2) 240VAC 20A receptacles. Regulatory CSA C22.2 No. 107.1-01, CSA C22.2 No. 0-M91 CSA C22.2 No. 0.4-04, CSA C22.2 No. 94-M91 UL 50, UL 1778 Table 2-2, GMR (Ground Mount) Specifications Notes: 1. Additional rack space capacity if batteries are not installed. 2. Runtime of 10 hours based on 212W load and new batteries at +25°C. 3. * Optionally configured items. 4. **Optional items shipped separately. 031-239-C0-003 Rev C 19 3.0 Installation CAUTION! Never transport the unit with installed batteries. Doing so can cause injury or damage to the enclosure and installed equipment. Install the batteries after you transport the unit to the site and secure it to the pole. CAUTION! Alpha recommends that you position the enclosure on the opposite side of the pole from oncoming traffic. This reduces the danger of falling equipment in the event that a pole is struck by an automobile. Mounting bolts must completely penetrate the wooden pole. Secure the bolts from the back with a large washer and nut. ATTENTION: The majority of poles belong to the local utility. Before you install an enclosure have both the location and mounting method approved by the utility. Because most codes require the enclosure to be located at a minimum height from the ground, always verify local height restrictions before you proceed. 3.1 PMR (Pole Mount) Installation 3.1.1 Enclosure on Wooden Pole Procedure: Materials and tools needed (customer supplied): • Two 5/8" diameter machine bolts, length to suit pole • Two 5/8" diameter zinc plated flat washers • Two 5/8" diameter hex nuts (UNC thread) • Auger or drill for boring 3/4" diameter holes in the wooden pole • Mallet or hammer • Assorted sockets • Tape measure 1. Unpack the enclosure and brackets; turn the enclosure facedown on a soft surface. 2. Slide a bracket into the enclosure’s lower mounting strap. The bracket’s flanges must face away from the enclosure. Secure the bracket to the mounting strap using a supplied 3/8" x 3/4" hex bolt. This pre-positions the lower mounting bracket, enabling you to accurately locate the placement of the lower mounting hole. 3. Mark the position for the upper mounting bracket on the utility pole. Drill a 3/4" hole completely through the pole. Secure the bracket to the pole with a 5/8" machine bolt, washer and nut. Do not fully tighten the bolt at this time. 4. Position the enclosure on the upper mounting bracket. If necessary, slightly rock the enclosure and pull downward to properly seat it on the bracket. Center the enclosure on the pole. 5. Mark the hole for the lower mounting bracket. Lift the enclosure off the top bracket and drill the lower hole. Spacing between holes for enclosures is as follows: PMR S-1 is 25 1/4" on center / PMR S-2 is 30.0" on center. 6. Slide the enclosure back into place over the top bracket. Align the lower bracket with the hole and secure it with a 5/8" machine bolt, washer and nut. Tighten both brackets until the flanges seat into the wood. 20 031-239-C0-003 Rev C 3.0 Installation, continued 3.1 PMR (Pole Mount) Installation, continued 3.1.1 Enclosure on Wooden Pole, continued The enclosure is now ready for the utility connection, power module, batteries, and nodes. 5/8" Bolt Upper Mounting Bracket Nut & Washer Chassis Ground 25.24" (PMR-S1) 30.0" (PMR-S2) Lower Mounting Bracket #8 AWG (minimum) Copper Ground Wire to 8 ft ground rod Nut & Washer 5/8" Bolt Fig. 3-1, Wooden Pole Installation 031-239-C0-002 Rev. B 21 3.0 Installation, continued 3.1 PMR (Pole Mount) Installation, continued 3.1.2 Enclosure on Short Pole with battery vault You can mount the PMR enclosure on a short wooden pole, in the same manner as on a standard utility pole, with an Alpha PS-6XL pedestal used as a battery vault. The accompanying illustrations are for reference, as the exact location of the vault will be a site-specific decision. NOTE: Install the pedestal as per the illustrations in Section 3.6 "Installing on a Polymer Pedestal Support". NOTE: Adhere to local codes regarding pole size, depth of hole, and fill material for hole and pedestal. The 8' length shown below is for reference only. Typically, one-third of the total length of the pole is buried. NOTE: Ground the system in the same manner as described in the previous section. 1 3 33.5" 96.0" 30.0" 7 2 32.0" 4 5 6 1 Pole mounting bracket centered on 6"x6" pole 5 3/8" pea gravel (2/3 of total depth of hole) 2 Grade 6 3" of 3/8" pea gravel 3 Fill dirt (to grade) 7 5/8-11 threaded rod (10" long) 4 Concrete cap (1/3 of total depth of hole) Fig. 3-2, Short Wooden Pole Installation 22 031-239-C0-003 Rev C 3.0 Installation, continued 3.1 PMR (Pole Mount) Installation, continued 3.1.2 Enclosure on Short Pole with battery vault, continued 1 1 Buried conduit for utility power, battery cables from vault,and node power cables (route conduit up post and secure to post). Actual location of conduit to be determined on site. Fig. 3-3, Top View 2 1 3/4" and 1/2" knockouts for battery vault conduit or power node cables. (4 places) 2 #8 AWG (min) Copper Ground Wire to 8 foot ground rod. 3 Utility Input Cable 4 Bottom of enclosure 1 3 4 Fig. 3-4, Connection Points 031-239-C0-003 Rev C 23 3.0 Installation, continued 3.1 PMR (Pole Mount) Installation, continued 3.1.3 Enclosure on Steel or Concrete Pole Materials and tools: • Two customer-supplied pole straps to fit pole • Assorted sockets Procedure: 1. Unpack the enclosure and galvanized brackets; turn the enclosure facedown on a soft surface. 2. Slide a bracket up through the enclosure’s lower mounting strap. The bracket’s flanges must face away from the enclosure. Secure the lower mounting bracket using the 3/8” x 3/4” hex bolt included. 3. Position the upper mounting bracket on the pole and secure using a pole strap. 4. Lift the enclosure onto the upper mounting bracket and pull downward to properly seat it. Center the enclosure on the pole. 5. Secure the lower mounting bracket on the pole using a pole strap. Spacing between mounting straps for enclosures is: PMR-S1 is 25.24" on center. and PMR-S2 is 30.0" on center. 6. The enclosure is now ready for the utility connection, power module and batteries. 24 031-239-C0-003 Rev C 3.0 Installation, continued 3.1 PMR (Pole Mount) Installation, continued 3.1.3 Enclosure on Steel or Concrete Pole, continued Pole Straps (customer supplied) Upper Mounting Bracket Chassis Ground Connector 25.24" (PMR-S1) 30.0" (PMR-S2) Lower Mounting Bracket #8 AWG (minimum) Copper Ground Wire to 8' Ground Rod Pole Straps (customer supplied) Fig. 3-5, Steel or Concrete Pole Installation 031-239-C0-003 Rev C 25 3.0 Installation, continued 3.2 GMR (Ground Mount) Installations 3.2.1 Pre-Installation Before you can install the GMR series enclosure, you must decide on the location, the type of mounting platform, and the connection and grounding options you will use. Several mounting options are available for this enclosure. You can mount an enclosure on a precast pad, pour-in-place pad using a template, or on an existing concrete pad. Things to consider: • Provide adequate room for service personnel to remove the doors for battery installation and removal. • Wherever possible, select a site that is above the 100-year flood plain, and away from residences. • Locate in the shade to minimize the effects of solar loading. • Locate in an area where airflow can be maximized. • Locate away from sprinkler systems or other sources of forced water. • Locate out of the prevailing wind to minimize the buildup of snow or accumulation of wind-borne dust. • Avoid locating the enclosure where it will be an obstruction or will inhibit visibility. • Evaluate the soil conditions for suitability for the installation of the required grounding system applicable to your particular installation. • Is utility power cabling run and terminated at the site? NOTE: The grounding method for a particular site will be dependent upon soil type, available space, local codes, NEC (National Electric Code), and other site-specific characteristics. ATTENTION: It is the responsibility of the installer to meet the requirements of all applicable national and local codes. Alpha Technologies assumes no responsibility or liability for failure of the installer to comply with the requirements of all applicable local and national codes. 26 031-239-C0-003 Rev C 3.0 Installation, continued 3.2 GMR (Ground Mount) Installations, continued 3.2.1 Pre-Installation, continued Alpha Technologies, Inc. cannot anticipate all of the ways a vehicle may potentially threaten an installed system or the specific type of protection that is appropriate for a particular location. The following installation drawing for Alpha’s Standby Power systems are general recommendations and not intended to be a specific guideline for protecting the equipment. The numbers of bollard posts (or other protection devices) depend upon equipment locations. 10’ (3m) SPRINKLER HEAD PAD POSTS SIDEWALK Fig. 3-6, GMR Positioning and Safety 031-239-C0-003 Rev C 27 3.0 Installation, continued 3.3 Enclosure Grounding NOTE: Alpha Technologies recommends using the grounding method illustrated below. The grounding method for a particular site will be dependant upon soil type, available space, local codes, NEC (National Electric Code), and other site-specific characteristics. NOTE: Alpha Technologies recommends 5 ohms minimum ground resistance between enclosure and ground rods, in accordance with IEEE 1100-1999 Powering and Grounding Electronic Equipment. NOTE: Alpha Technologies assumes no responsibility or liability for failure of the installer to comply with the requirements of all applicable local and national codes. Where allowed, exothermic welding may be used as an alternative to Burndy clamps and connectors. Connection made with Burndy connector (P/N YGHR58C2W-3 or equivalent) Terminate at enclosure ground 2 et fe ) in (m %NCLOSURE&OOTPRINT Terminate at service entrance ground #6 AWG #2 AWG Two (2) 8' ground rods 6' apart minimum. Note: May require additional ground rods to meet NEC minimum grounding standard (25 Ohms or less). Connection made with Burndy connector (P/N YGHP58C2W-2TN or equivalent) Fig. 3-7, Suggested Grounding Method 28 031-239-C0-003 Rev C 3.0 Installation, continued 3.4 Installing Enclosure on Pre-cast Pad 2.50 Alpha offers a Polymer Precast Pad option to speed installation of a GMR series enclosure. To install the precast pad, prepare a layered bed of sand and gravel before placing the pad on top. For specific information, consult the instructions that accompany the precast pad. The dimensioned drawing below applies to the precast pad mentioned, but can also be used to lay out a pour-in-place concrete pad. An optional vapor barrier (p/n 564-990-10), or rubber pad vapor barrier (p/n 641-123-10) may be used as a template. 2.50 DIA THRU 3/8-16 UNC THREADED INSERT 4 PL 14.75 10.75 10.00 7.500 A 0.500 27.00 A .000 4.75 29.00 24.00 23.00 7.5 3.00 .000 1.50 10.00 10.50 3.00 44.00 Section A-A Fig. 3-8, Layout for Precast Pad, Single-wide for GMR Series Enclosures Alpha P/N 641-112-10 031-239-C0-003 Rev C 29 3.0 Installation, continued 3.5 Conduit Routing Area, GMR-S1 Enclosure During installation, verify conduit is routed through the shaded area in Section B-B below. PAD OPENING 16.0 2.9 2.6 1.0 BRING CONDUIT UP WITHIN THIS AREA Section B-B ® B GMR-S1 B Fig. 3-9, Conduit Routing Area 30 031-239-C0-003 Rev C 3.0 Installation, continued 3.6 Conduit Routing Area, GMR-S2 Enclosure During installation, verify conduit is routed through the shaded area in Section A-A below. 14.8 3.9 1.6 5.2 PAD OPENING Section A-A BRING CONDUIT UP WITHIN THIS AREA ® A A GMR-S2 Fig. 3-10, Conduit Routing Area 031-239-C0-003 Rev C 31 3.0 Installation, continued 3.7 Installing on a Polymer Pedestal Support Alpha’s Polymer Pedestal Support system provides a quick, one-step solution for installing a GMR series enclosure. Contact Alpha Technologies Customer Service (1-800-863-3930) to determine which Pedestal Support best suits your requirements. NOTE: The GMR-S2 will be slightly off center when mounted on a polymer pedestal or pad. This does not affect performance. 35 .75 " 35 .75 .0" 24 .0" " 24 25 .75 43 .2" " .5" 19 " .75 31 Fig. 3-12 PS-6XL Pedestal Alpha P/N 745-324-21 Fig. 3-11, PS-6 Standard Pedestal Alpha P/N 745-324-20 PRECAST PAD GRADE BACK-FILL UTILITY OPTIONAL PEDESTAL SUPPORT OUTPUT SWEEP 6 TO 12 INCHES OF COMPACTED GRAVEL UNDISTURBED GROUND Fig. 3-13, Typical Pedestal Site 32 031-239-C0-003 Rev C 4.0 Equipping the System 4.1 Service Power ATTENTION: • Use qualified service personnel to connect to utility power in compliance with local electrical codes and common safety practices. Connection to utility power must be approved by the local utility before you install the power supply. • UL and NEC require that a UL-listed service disconnect switch be installed between the power source and the power supply. Connection to the power supply must include an appropriate service entrance weather head. NOTE: Utility power enters the enclosure through a 70 A rainproof SUSE-rated breaker box. to utility L1 (black) neutral (white) Copper ground wire #8 AWG (minimum) breaker neutral bus grounding point made to enclosure wall L1 (black) 120VAC Service Entrance Wiring to enclosure receptacle L1 (black) Neutral (white) Ground (green) 120VAC/20A Receptacle -- 5-20R Fig. 4-1, Service Power 031-239-C0-003 Rev C 33 4.0 Equipping the System, continued 4.2 Batteries WARNING! Battery systems represent a risk of electrical shock and high short circuit currents. The following precautions must be observed when maintaining batteries: • Remove all personal metal objects (watches, rings, etc.) • Use insulated tools. • Wear eye protection and rubber gloves. • Observe circuit polarities. • Do not make or break live circuits. • Do not lay metal tools and hardware on top of the batteries. The batteries are enclosed in cabinets with limited access. Again, extreme caution must be exercised when maintaining and collecting data on the battery system. Battery Identification Each battery contains a DATE CODE usually located on a sticker between the battery posts. This date code must be recorded in the battery’s maintenance log. If batteries other than those installed by Alpha are used, consult the battery’s documentation for date code type and placement. Battery Date Code located in this box (0605 = June 2005) Fig. 4-2, Battery Identification Label 34 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.2 Batteries, continued 4.2.1 PMR Batteries Batteries are placed on the floor of the enclosure and connected in accordance with the accompanying Battery Cable Kit instruction sheet. Red NOTE: To install AlphaCell gel batteries, place the batteries (on their side) into the bottom of the enclosure with the positive terminal facing UP, and connect the battery cable kit as shown. For detailed instructions, refer to the instruction sheet that accompanies the Battery Cable Kit. Wire tie locations 3/4" Knockouts Fuse 1/2" Knockouts Black 48V 36V 24V 12V 4A 3A 2A 1A RTS probe Optional Battery Retainer Bar Optional AlphaCell 50Ah 85GXL Batteries Fig. 4-3, Battery Installation for PMR Series (Standard Battery Cable Kit Shown) 031-239-C0-003 Rev C 35 4.0 Equipping the System, continued 4.2 Batteries, continued 4.2.2 GMR Batteries Batteries are placed on the floor of the enclosure and connected in accordance with the accompanying Battery Cable Kit instruction sheet. NOTE: To install AlphaCell gel batteries, place the batteries (on their side) into the bottom of the enclosure with the positive terminal facing UP, and connect the battery cable kit as shown in Fig. 4-3. For detailed instructions, refer to the instruction sheet that accompanies the Battery Cable Kit. Fig. 4-4, Battery Installation for GMR Series Rear View, Doors and Lid Removed 36 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.3 Mounting Rail Adjustment The equipment mounting rails are held in place by #10-32 hardware at the top and bottom of each rail. The distance between each stud (upper) and threaded hole (lower) is 1". The seven studs and seven threaded holes provide six mounting positions for specific customer applications. To reposition the rails, remove the screws or nuts and slide the rail forward or backward to the next set of holes or studs and replace the screws or nuts. PMR enclosure Fig. 4-5, Left side Mounting Rail (as viewed from front of enclosure) 031-239-C0-003 Rev C PMR enclosure Fig. 4-6, PMR Right side Mounting Rail (as viewed from front of enclosure) GMR enclosure Fig. 4-7, GMR Right side Mounting Rail (as viewed from rear of enclosure) 37 4.0 Equipping the System, continued 4.3 Mounting Rail Adjustment, continued Fig. 4-8, GMR/PMR enclosures, upper left side rail detail Fig. 4-9, PMR enclosure, upper right side rail detail Fig. 4-10, Lower rail detail (common to GMR and PMR enclosures) 38 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.4 Power Supply Installation 17.45" Optional Mounting Bracket P/N 745-265-20 15.96" The power supply can be mounted on four studs located on the upper left wall of the enclosure (for S2 enclosures) or on the mounting rail (for S1 and S2 enclosures). Reference the following drawings for location. For detailed installation and wiring instructions, refer to the installation and operation manual that accompanies the power supply. 9.24" 26.69" Optional ELPM 300W Power Supply. Fig.4-11, Power Supply Location, PMR, GMR-S1 Enclosure 031-239-C0-003 Rev C 39 4.0 Equipping the System, continued 4.4 Power Supply Installation, continued 1 2 3 4 5 10” (25.4cm) 6 7 8 9 10 Fig. 4-12, Power Supply Location, Enclosure Features PMR/GMR-S2 Enclosure Inside View, Left Wall Optional FlexNet Power Supply 7 Ground Bar, 5 position 2 Adjustable Equipment Rack, 6 Positions 1" Centers 8 Optional Fiber Slpice Module 3 Water Deflector 9 Optional AlphaCell 85GXL Batteries 4 Drain 10 Access panel for Generator or Portable Generator 5 Optional 120VAC/20A Dual Duplex Outlets 6 Optional Fiber Management Panel 1 40 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.5 GMT Fuse Module 4.5.1 Installation During normal operation, the FlexNet Fiber UPS (model ELPM300-48D) is powered by 120VAC or 240VAC line input or 48VDC battery string. The UPS supplies 48VDC, 300W power to the GMT Fuse Module (p/n 747-218-20) and on to any customer-supplied equipment within the enclosure. Output power is provided through the optional GMT Fuse Module. You can fix the module to the bottom arm of the swing rack, or to the left side of the fixed equipment rack in the GMR Series Enclosures. Four 4-position headers provide connection points for ground and 48VDC output. Two of the headers are "Common" and the other two headers allow for fused connections. The wire connection is accomplished by stripping 1/4" of wire, inserting it into the appropriate header position and tightening in place with a .100" jeweler's screwdriver. Fig. 4-13, Placement of #10-32 Tinnerman Nuts Fig. 4-15, GMR S-2 Location Fig. 4-14, GMT Fuse Assembly Secured to Rail Fig. 4-16, PMR S-2 Location (On Swing Rack) WARNING! Verify power is off before making connections. 031-239-C0-003 Rev C 41 4.0 Equipping the System, continued 4.6 Internal Connections 4.6.1 System Block Diagram GMT Fuse Module (p/n 747-218-20) Connect equipment between common (+) and one of the fused positions (-) for -48VDC output. Hot connections allow UPS hot swap + + + + - - - - Fuse Fig. 4-17, Simplified Block Diagram (Hot Swap with GMT Distribution Battery Cable Kit) 42 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.6 Internal Connections, continued 4.6.2 "Hot-Swap" Procedure The battery cable kit is designed so you can remove and replace the UPS while continuing to provide power to downstream equipment (hot-swapping). WARNING! The connector pair is used for hot swapping the UPS in the event it needs service or replacement. Failure to disconnect this connector pair will result in pemanent battery damage. Tools required: 3/8" socket, wrench, and extension 1. Make "hot-swap" connection (leads and connectors are pre-wired in battery cable harness). The load is supplied by the battery string during hot-swap. 2. Disconnect Input, Output connectors from UPS to be replaced. 3. Remove "Nylock" nuts (4 places). 4. Install replacement UPS. 5. Reconnect Input,Output connectors to power supply. 6. Disconnect 'hot-swap" connection. UPS to be replaced 3 3 2 1, 6 + + + + - - 4 - 4 - Replacement UPS 5 Fig. 4-18, Connections for "Hot-Swapping" the UPS 031-239-C0-003 Rev C 43 4.0 Equipping the System, continued 4.7 Fiber Management Panel The optional Fiber Management Panel (Alpha p/n 745-672-20) provides fiber slack storage and secures a splice tray using a Velcro strap. The side tie wrap slots permit securing fiber cables to panel. The panel is easily installed on the left side of the enclosure (as viewed from the front) and slides over two wall-mounted studs at the top of the panel, held in place by #10-32 screws, and secured by a wingnut at the center bottom of the panel. 9.5" (24.13cm) 1 16" (40.64cm) 2 3 4 5 6 Fig. 4-19, Fiber Management Panel 44 1 12-position Fiber Splice Tray (p/n 565-033-10) 4 Tie Slots 2 Velcro Cinch Strap (p/n 660-112-10) 5 Cable Clip, 5 PLC. (p/n 651-667-10) 3 Strain Relief Kt (p/n 745-649-20) 6 Central Member Clamp, 4 PLC. 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.8 Optional Fan Kit Installation The 48VDC and 120VAC fan option for PMR and GMR Series enclosures supplies cooling for equipment rated to 55°C (131°F) ambient internal temperature. See Section 2.1 and 2.2 for Alpha part numbers and specifications. The fan unit mounts easily inside the enclosure by sliding the flanges, located at the rear of the unit, into the slot on the back wall of the enclosure and then extending the side rails until they are secure. 3 1 2 4 5 Fig.4-20, Optional Fan Kit 1 Power Cord 4 Right-side Fan* 2 Wiring Kit 5 Right-side Sliding Rail* 3 Right-side Rear Flange* *Note the corresponding component on the left-side of the unit 031-239-C0-003 Rev C 45 4.0 Equipping the System, continued 4.8 Optional Fan Kit Installation, continued To install the fan kit: 1. Remove the enclosure lid. 2. Holding the fan unit, with side flanges toward the rear of the enclosure, slide the flanges into the slot under the rear lip of the enclosure. See Fig. 4-21. 3. After the rear of the unit is firmly placed, loosen the wing nuts on the slide rails. 4. Extend the rails until they are firmly seated against the front of the enclosure. Tighten the wing nuts. 5. Plug the power cord into the outlet located on the left side of the enclosure. 6. Replace the lid of the enclosure. Fig. 4-21, Placing Fan Unit Fig. 4-22, Extending Side Rails Fig. 4-23, Completed Fan Install 46 031-239-C0-003 Rev C 4.0 Equipping the System, continued 4.9 Optional Form C Alarm Panel Installation The PMR and GMR Series enclosures can be modified to supply Form C alarm signals. The optional Form C Alarm Panel installs easily into the equipment mounting rack and plugs into the ELPM 300W power supply, using supplied wiring kits. See Section 2.1 and 2.2 for part numbers and specifications and the ELPM 300 manual for specific information on the power supply. 2 1 3 4 1 Plug into the AC Power outlet at the rear of the enclosure 2 Plug into the Status Monitoring connector on the ELPM front panel 3 Plug into the Output connector on the ELPM front panel 4 Provides connection for customer-supplied monitoring equipment. 5 Provides for customer-supplied alarm monitoring with the addition of a "Rectifier Fail" alarm. 5 1.00 Fig. 4-24, Form C Alarm Signal Panel 1.98 18.12 19.00 Fig. 4-25, Form C Alarm Signal Panel Dimensions 031-239-C0-003 Rev C 47 4.0 Equipping the System, continued 4.9 Optional Form C Alarm Panel Installation, continued 4.9.1 Mounting and Wiring the Alarm Panel 1. Fasten the panel to the rack using the screws supplied with the rack system. 2. Make the following connections from the front of the alarm panel to the front panel of the ELPM, using the appropriate wires from the wire kit. See Fig. 4-26 for details. From Alarm Panel To ELPM Power Supply Line Sense AC Power To ELPM Alarm Status monitoring connector To ELPM Output Output Fig. 4-26, Attach panel to rack Table 4-1, Connections for Alarm Panel 3. Complete the VOut and Alarm connections (see Fig. 4-24) to your monitoring equipment. ELPM Power Supply Form C Alarm Panel To AC Power To Status Monitoring Connector To ELPM Output To Customer Equipment Fig. 4-27, Wiring the Alarm Panel 48 031-239-C0-003 Rev C Power Alpha Technologies ® Alpha Technologies 3767 Alpha Way Bellingham, WA 98226 USA Tel: +1 360 647 2360 Fax: +1 360 671 4936 Web: www.alpha.com Alpha Technologies Ltd. 4084 McConnell Court Burnaby, BC, V5A 3N7 CANADA Tel: +1 604 430 1476 Fax: +1 604 430 8908 Alpha Technologies Europe Ltd. Twyford House Thorley Bishop's Stortford Hertfordshire CM22 7PA UNITED KINGDOM Tel: +44 0 1279 501110 Fax: +44 0 1279 659870 Alpha Technologies GmbH Hansastrasse 8 D-91126 Schwabach GERMANY Tel: +49 9122 79889 0 Fax: +49 9122 79889 21 Alphatec, Ltd P.O. Box 56468 Limassol, Cyprus CYPRUS Tel: +357 25 375675 Fax: +357 25 359595 AlphaTEK ooo Khokhlovskiy Pereulok 16 Stroenie 1, office 403 109028 Moscow RUSSIA Tel: +7 495 916 1854 Fax: +7 495 916 1349 Alphatec Baltics S. Konarskio G. 49 Vilnius 2009 LITHUANIA Tel: +350 5 210 5291 Fax: +350 5 210 5292 Alpha Technologies 5 Avenue Victor Hugo F-92140 Calmart France FRANCE Tel: +33 3 41 90 07 07 Fax: +33 1 41 90 93 12 Due to continuing product improvements, Alpha reserves the right to change specifications without notice. Copyright © 2006 Alpha Technologies, Inc. All rights reserved. Alpha is a registered trademark of Alpha Technologies. 031-239-C0-003 Rev. C.