Preview only show first 10 pages with watermark. For full document please download

Xcel Energy – Telemetry Requirements For Distributed Energy

   EMBED


Share

Transcript

Xcel Energy – Telemetry Requirements for Distributed Energy Resource Interconnections Communications Enclosure Mounting Details: • The Customer shall provide a location to mount the enclosure. The enclosure is approximately 20”x20”x12” with Unistrut mounts across the top and bottom. • The enclosure should be mounted such that the bottom of the cabinet is between 2’-4’ off the ground. • The install location is preferred to be on a stand-alone pedestal, but can be along the side of a building as long as it does not cause cellular interference. There must also be a location to install an AC disconnect near the enclosure mount location. o The disconnect is a Square D Safety Switch, model H221NRB and must be mounted near the communications enclosure. Customer must provide a suitable place to mount within 6’ of the enclosure location. • The enclosure and disconnect will be dropped off at the customer location for installation. It is the customer’s responsibility to mount the enclosure and the disconnect switch as well as connect the AC power to the disconnect, run power from the disconnect to the enclosure. Power Source Details: 120VAC, 15A circuit, #10 CU minimum, to be provided from Customer’s panel • To be connected to Xcel Energy owned fused-disconnect switch. • Circuit must be run in conduit from power source to bottom of fused-disconnect mounting location and in conduit from the disconnect to the enclosure following applicable NEC standards. Communications Details: Two communication methods are available for the Customer to select from between the meter and the communications enclosure, Ethernet or Fiber. For either solution, the Customer will provide all wiring, connectors, switches, panels and any other hardware to meet the requirement. Any failure of equipment downstream of the communications panel is the Customer’s responsibility to fix within an expeditious time frame. Communications to all Xcel Energy meters on site is required. For Ethernet: Requirements: - Industrial / Ruggedized Cable, RJ45, Cat5, in conduit from meter location to communication enclosure • One Ethernet cable per meter; to be connected between the meter and the Xcel Energy owned enclosure. o For single sites (two total meters), the Customer may run both cables individually to the enclosure. o For co-located sites, the Customer must use an Ethernet Switch to provide a single cable connection to the communications panel as the enclosure cannot accept more than two Ethernet cables. o Maximum recommended distance for Cat5 cable is 100 meters (328 feet.) o For sites with distances greater than 100m between meter and communications panel, Fiber is recommended. For Fiber: Requirements: Mode: Multimode, Fiber core size: 50 micron (50/125um), Range: 500m, Wavelength: 850nm, 100BASE-FX. In conduit to communications panel • Customer to run fiber from each meter to a patch panel. The Customer is required to install the patch panel for the fiber and provide the single fiber pair to the communications panel. • Customer must provide the Fiber to Ethernet media converter for Ethernet connection to each meter. • Customer must provide the end-cap on the fiber to connect to the bulkhead of the enclosure. o The connector required is duplex LC Additional Details: • For customers with more than five co-located DER sites, it is required that the Customer provide an RTU to aggregate the data from the meter to provide a single point of contact to poll data from the meters. Xcel Energy engineering will work with the Customer on this as needed. Else, a 2nd communications enclosure will be required. • A combination of communications technologies can be utilized at the Customer’s discretion. For example, Fiber could be used to all meters, with Ethernet to the enclosure or vice versa.